Projects Progress

BTO TOP Tracker

Estimated T-O-P
HDB starts distributing keys to unit ownsers.
Delivery Possession
All projects keys distribution completed.
Estimated M.O.P
Minimum Occupation Period

Almost there!

Northshore Edge - (2021-12-01)
May delay up to 10 month(s) 2022-10-01
100% Complete
Woodlands Glade - (2021-12-01)
🦠 Covid19: May delay up to 10 month(s) 2022-10-01
100% Complete
Melody Spring @ Yishun - (2021-12-01)
🦠 Covid19: May delay up to 11 month(s) 2022-11-01
100% Complete
🦠 Covid19: May delay up to 11 month(s) 2022-11-01
100% Complete
Ubi Grove - (2021-12-01)
🦠 Covid19: May delay up to 12 month(s) 2022-12-01
100% Complete
Woodleigh Village - (2021-12-01)
🦠 Covid19: May delay up to 12 months(s) 2022-12-01
100% Complete
🦠 Covid19: May delay up to 9 month(s) 2022-12-01
100% Complete
Anchorvale Village - (2022-03-01)
🦠 Covid19: May delay up to 9 month(s) 2022-12-01
100% Complete
Tampines GreenCourt - (2022-03-01)
🦠 Covid19: May delay up to 9 month(s) 2022-12-01
100% Complete
Yishun Glen - (2022-03-01)
🦠 Covid19: May delay up to 10 month(s) 2023-01-01
98% Complete
Eunos Court - (2022-03-01)
🦠 Covid19: May delay up to 12 month(s) 2023-03-01
96% Complete
Marsiling Grove - (2022-03-01)
🦠 Covid19: May delay up to 12 months
96% Complete
Clementi NorthArc - (2022-06-01)
🦠 Covid19: May delay up to 9 month(s) 2023-03-01
96% Complete
Woodleigh Hillside - (2022-06-01)
🦠 Covid19: May delay up to 10 month(s) 2023-04-01
95% Complete
Tampines GreenVines - (2022-06-01)
🦠 Covid19: May delay up to 9 month(s) 2023-03-01
95% Complete
Fernvale Dew - (2022-06-01)
🦠 Covid19: May delay up to 10 month(s) 2023-04-01
93% Complete
Teck Whye View - (2022-06-01)
🦠 Covid19: May delay up to 12 month(s) 2023-06-01
91% Complete
Keat Hong Verge - (2023-03-01)
91% Complete
MacPherson Blossom - (2023-06-01)
90% Complete
Jurong West Jewel - (2022-06-01)
🦠 Covid19: May delay up to 12 months(s) 2023-06-01
89% Complete
Kallang Breeze - (2022-09-01)
🦠 Covid19: May delay up to 9 month(s) 2023-06-01
89% Complete
Kim Keat Beacon - (2022-09-01)
🦠 Covid19: May delay up to 10 month(s) 2023-07-01
89% Complete
Rivervale Shores - (2022-09-01)
🦠 Covid19: May delay up to 12 month(s) 2023-09-01
88% Complete
Punggol Point Woods - (2023-03-01)
🦠 Covid19: May delay up to 6 month(s) 2023-09-01
85% Complete
Boon Lay Glade - (2022-09-01)
🦠 Covid19: May delay up to 12 month(s) 2023-09-01
84% Complete
Plantation Acres - (2022-12-01)
🦠 Covid19: May delay up to 9 month(s) 2023-09-01
83% Complete
Tampines GreenGem - (2023-06-01)
🦠 Covid19: May delay up to 7 months(s) 2024-01-01
79% Complete
Punggol Point Cove - (2023-01-01)
🦠 Covid19: May delay up to 14 months(s) 2024-03-01
78% Complete
Fernvale Vines - (2023-01-01)
🦠 Covid19: May delay up to 12 months(s) 2024-01-01
78% Complete
Champions Green - (2023-12-01)
78% Complete
Plantation Grange - (2022-12-01)
🦠 Covid19: May delay up to 12 month(s) 2023-12-01
76% Complete
Tampines GreenSpring - (2023-03-01)
🦠 Covid19: May delay up to 9 month(s) 2023-12-01
76% Complete
Yio Chu Kang Beacon - (2023-12-01)
76% Complete
Tampines GreenGlade - (2023-09-01)
76% Complete