Projects Progress

BTO TOP Tracker

Estimated T-O-P
HDB starts distributing keys to unit ownsers.
Delivery Possession
All projects keys distribution completed.
Estimated M.O.P
Minimum Occupation Period

Halfway there!

Kempas Residences - (2024-09-01)
🦠 Covid19: May delay up to 10 months(s) 2025-07-01
75% Complete
Kebun Baru Edge - (2025-03-01)
73% Complete
ParkView @ Bidadari - (2025-03-01)
72% Complete
Tampines GreenEmerald - (2025-03-01)
72% Complete
Parc Woods @ Tengah - (2025-03-01)
70% Complete
Tampines GreenOpal - (2025-06-01)
69% Complete
Dakota One - (2025-06-01)
69% Complete
Bishan Towers - (2025-06-01)
69% Complete
Parc Clover @ Tengah - (2024-12-01)
68% Complete
Sun Sails - (2025-06-01)
68% Complete
Bartley Beacon - (2025-06-01)
68% Complete
Parc Glen @ Tengah - (2024-12-01)
68% Complete
66% Complete
Hougang Citrine - (2025-03-01)
66% Complete
Grove Spring @ Yishun - (2024-12-01)
65% Complete
Hougang Olive - (2025-03-01)
63% Complete
Garden Bloom @ Tengah - (2025-09-01)
60% Complete
Costa Grove - (2025-12-01)
🦠 Covid19: May delay up to 6 months(s) 2026-06-01
58% Complete
Tampines GreenJade - (2025-09-01)
58% Complete
UrbanVille @ Woodlands - (2026-06-01)
58% Complete
Yishun Boardwalk - (2025-06-01)
56% Complete
Bishan Ridges - (2026-06-01)
🦠 Covid19: May delay up to 4 month(s) 2026-10-01
53% Complete
Nanyang Opal - (2025-12-01)
52% Complete
ParkEdge @ Bidadari - (2025-03-01)
🦠 Covid19: May delay up to 17 months(s) 2026-08-01
52% Complete
Parc Flora @ Tengah - (2025-09-01)
52% Complete
Toh Guan Grove - (2026-03-01)
51% Complete