Projects Progress

BTO TOP Tracker

Estimated T-O-P
HDB starts distributing keys to unit ownsers.
Delivery Possession
All projects keys distribution completed.
Estimated M.O.P
Minimum Occupation Period

Quaterway there!

Kempas Residences - (2024-09-01)
49% Complete
Tampines GreenGlade - (2023-09-01)
44% Complete
Kim Keat Ripples - (2024-06-01)
43% Complete
Canberra Vista - (2024-09-01)
40% Complete
Tampines GreenCrest - (2023-12-01)
40% Complete
Toa Payoh Ridge - (2025-03-01)
36% Complete
Champions Bliss - (2024-09-01)
33% Complete
Garden Court @ Tengah - (2024-03-01)
33% Complete
33% Complete
Kebun Baru Edge - (2025-03-01)
29% Complete
Bishan Towers - (2025-06-01)
28% Complete
Dakota One - (2025-06-01)
28% Complete
Tampines GreenOpal - (2025-06-01)
28% Complete
26% Complete
25% Complete
Alkaff Breeze - (2024-06-01)
25% Complete
ParkView @ Bidadari - (2025-03-01)
25% Complete
Tampines GreenEmerald - (2025-03-01)
25% Complete
Costa Grove - (2025-12-01)
25% Complete